Home

Example 1 - Bricks

Photograph of a brick wall.A builder requires a particular brick for external cladding. In the quoting process the builder is told they need to give two weeks notice prior to the delivery date required. In the job schedule the builder can see that two weeks prior to needing the bricks is the time scheduled for placing the footing. The builder can:

  • make a note against the task in the project schedule next to footings
  • make a note on the call forward sheet.