If pipes are laid under the slab they should be located wholly under the slab where possible. Extra bottom mesh should be placed over the pipe to avoid any weakening of the slab.
Box-outs for bath, shower bases and similar plumbing fixtures should be placed carefully to minimise weakening of the slab.
Note: Electric heating cables may be embedded in the slab without any increase in thickness or reinforcement.