| Task ID | Task | Days | Preceding events |
|---|---|---|---|
| 52 | Lock up complete | 0 | |
| Fixing and fittings | |||
| 53 | Plaster walls | 5 | 52 |
| 54 | Internal joinery (cupboards, pantries, built-in robes etc) | 4 | 53 |
| 55 | Fix skirting boards, architraves | 3 | 54 |
| 56 | Fit internal doors | 3 | 55 |
| 57 | Plumbing fit-off | 2 | 56 |
| 58 | Electrical fit-off | 3 | 54 |
| 59 | Painting | 10 | 56 |
| 60 | Gas inspection | 0.5 | 57 |
| 61 | Electrical inspection | 0.5 | 58 |
| 62 | Sewerage inspection | 0.5 | 57 |
| 63 | Complete fittings and fixtures | 0 | 59, 61, 62 |