Task ID | Task | Preceding event | Nodes |
---|---|---|---|
A | Make enquiries and order all materials required | Start | 1 |
B | Wait for bricks, sand and cement to arrive | A | 2 |
C | Clear vegetation from the site | A | 2 |
D | Order concrete to be delivered | A | 2 |
E | Dig the trench | C | 4 |
F | Pour the footings | E | 5 |
G | Footings curing time | F | 6 |
H | Load the bricks on the site | B | 3 |
I | Mix the mortar and lay the bricks | H | 7 |
J | Clean rubbish from the area | I | 8 |
Finish | J | 9 |